|
Decks are a perfect area for outdoor
entertaining and outdoor relaxing.
The style of deck you choose to
build determines how you use your
deck, as well as how you build it.
Although similar in appearance,
different decks can require
different construction techniques.
Our Installation Services experts
built this Ground-Level deck and
documented the steps taken in order
to help you build your own outdoor
living area.
You will see how the deck was
assembled, why material choices were
made, and the approximate time it
took to do the work. Use this
example to help you plan your own
deck.
|
SKILL SCALE
Hard
TIME
REQUIRED
Experienced:
2 day
Handy: 3 1/2 days
Novice: 4 days
TOOLS
Stud finder
MATERIALS
|
| STEPS |
|
| 1 |

|
Batterboards
and mason's string lines were used
to lay out footing locations for a
deck that is approximately 8 feet
wide and 10 feet long. Six holes for
8-inch-diameter footings were dug
with a posthole digger. Each hole is
12 inches deep. There is no frost
line to deal with since this is a
freestanding deck. Tube forms were
used to level the footings about 1
inch above ground level.
Approximate time for a novice
(with a helper) to lay out footing
locations, dig holes and level tube
forms for this deck: 5-7 hours.
|
|
|
| 2 |

|
Six
60-pound bags of ready-mix concrete
were mixed in a wheelbarrow. Post
anchors for 4x4 posts were attached
to the footings after the concrete
cured for 48 hours. The anchors were
aligned with a long straight board.
Diagonal measurements were checked
to square the anchor positions.
Approximate time (not including
curing time): 3-4 hours
|
|
| 3 |
 |
Beams
were made from double 2x6s. They
were attached in the post anchors. A
1/2-inch-thick pressure-treated shim
was installed between the beam and
one side of the anchor at each
footing. The anchor is 3 1/2 inches
wide and the beam is 3 inches thick.
Approximate time: 2-3 hours.
|
|
| 4 |
 |
Beam
alignment was checked and adjusted
as necessary to make certain beams
were square.
Approximate time: 1/2-3/4 hour.
|
|
| 5 |
 |
2x6
rim joists were attached to the ends
of the beams. Angle brackets were
installed to provide additional
support for the corner joints.
Approximate time: 1-1 1/2 hours.
|
|
| 6 |
 |
Inner
2x6 joists were attached to the beam
faces with joist hangers.
Approximate time: 3-5 hours.
|
|
| 7 |
 |
2x6
decking was installed perpendicular
to the joists. Decking was fastened
with deck screws. Ends of boards
hang over edge of deck and will be
trimmed to length after
installation.
Approximate time: 1 1/2-2 hours.
|
|
| 8 |
 |
A
chalk line was snapped to mark a
straight cutting line. Decking was
trimmed to length with a circular
saw.
Approximate time: 1/4-1/2 hour.
Total approximate time for this
ground-level deck:
16-24 hours.
|